

Have you wondered why certain project tasks can be postponed without triggering frenzy, and others send everyone into a crisis? I have experienced the "ticking clock" and multiple deadlines firsthand. The answer is familiarity with Slack, which is a hallmark of project managers who are successful, as opposed to those who are in a constant state of firefighting.
Slack, or float, is the measure of how long a task can be postponed without affecting the due date of the project or the subsequent activities. It is a measure of how much "spare" time you have in your schedule. If you are heading towards your PMP certification training, then this is a concept you need to master, because it is one of the key areas tested on the certification exam and is critical in the practical side of project management.
In the world of project management, slack refers to the degree of flexibility in the schedule. It encompasses the gap or "cushion" that exists between the "must-be-done" and the "can-be-done." When it comes to the language of project management, float and slack are synonymous. Most practitioners use the terms interchangeably, although in official documents, PMI is likely to prefer "float."
The importance of Slack in scheduling is that rather than seeing all the tasks that need to be done as equally important, you can start to see which activities are time sensitive and need to be addressed andidentified, and which ones are more flexible to take place at a later time. This enables you to better resource and manage the teams and their workloads, and sets more reasonable expectations with stakeholders.
The principle of slack directly correlates to network diagrams and the critical path method (CPM). After laying out the project activities with their corresponding dependencies, Slack values are calculated and are used to describe the flexibility of the schedule.
Free float is the amount of time you can delay a task before it has an impact on the early start of any subsequent tasks. The calculation is quite simple:
Free Float = ES (subsequent task) - EF (current task)
Here's a simple example. Assume that Task A is done on Day 5, and Task B (which is dependent on Task A) can be scheduled to start on Day 7. Task A has a free float of 2 days. You can delay Task A by 2 days and still have Task B start on Day 7.
When it comes to dealing with resource-related challenges, adaptability like this is priceless. If an employee requires an additional day to complete Task A and you see that it has available free float, you can adapt to this resource change without any negative impact.
Total float indicates the amount of flexibility an activity can have so as not to impact the finishing deadline of the project. It can be calculated as follows:
Total Float = LF - EF or LS - ES
Where:
Total float is always greater than or equal to free float. When an activity is part of more than one path, it is possible for the activity to have the same total float, and this means that when float is utilised on an activity, the available float for subsequent activities in that sequence is reduced.
Here is a revised table that explains what each aspect means.
| Type | Definition | Impact | Formula |
| Free Float | Delay that does not impact successor tasks | Task-level only | ES(next) - EF(current) |
| Total Float | A delay that does not impact the completion of the project | Project-level | LF - EF or LS - ES |
| Project Float | The period between the scheduled completion and the deadline that is set | Overall schedule | Deadline - Planned Finish |
In some instances, a float is calculated, and a negative number is the result. This does not represent a math error; it is a sign that something is wrong. In fact, negative float means the project is behind schedule, if not already behind schedule to begin with, or some delays have pushed the project past the deadline.
In most cases, negative float means that difficult choices have to be made, such as crashing (adding more resources), fast-tracking (concurrent task execution), or renegotiating to extend the deadline. In my experience, identifying negative float with the help of PMP formulas in conjunction with frequent updates can save a great deal of time and effort in the future.
The critical path is the longest chain of dependent activities in a given project. Activities within this path are commonly devoid of slack - meaning that any delay will have a direct impact on the project's end date.
So, why zero? Because these activities are linked together without any buffer time. In the example, Task 1 takes 5 days, Task 2 takes 3 days, and Task 3 takes 4 days. That's 12 days, and there is no slack to absorb delays.
It's important to know that not all critical path tasks have to have float. In some cases, project managers build in some buffers deliberately as a risk mitigation strategy. Ultimately, low or zero float is screaming for your attention the most.
As for non-critical path tasks, there is plenty of flexibility. If a task has 5 days of total float, it can be pushed for a week, and this will not affect the plan at all. This will help when optimising your top priorities.
To calculate float manually, there are two main steps: forward pass and backward pass on your network diagram.
Forward Pass identifies the earliest you can start and finish tasks:
Backwards Pass — you Backwards Pass the final activity first, and set this to LF = EF:
Then you are able to find the Float, by Simple Subtraction:
I'll be honest, manual calculations are useful for the understanding and the conceptual reasoning of the test answer; otherwise, I just use project management software for actual work. The tools compute this information to be updated from schedule changes. In the Techademy PMP certification course, you will have the opportunity to use both methods.
It is crucial to keep an eye on the Total Float. It serves as an indicator of how close we are to hitting an impending deadline. When I notice multiple activities with low float values, this is an indicator of schedule pressure, even before we start to run late. This lets you make an adjustment before it's too late. You can increase resources, change the scope of work, or notify stakeholders.
In general, projects will have protective time buffers/float built into their timelines and budgets to allow for better management of unforeseen circumstances, including equipment failures, employee illnesses, and clarifications to the project scope.
Float helps alleviate some of the pressure and improves the morale of the team. With more float, project managers are better able to allocate resources to the appropriate areas. Teams can be more comfortably assigned to non-critical float-task areas, enabling better utilisation of the team.
There are also positive psychological effects to be gained by the use of float. Team burnout can be avoided. When absolutely everything is "urgent", the team is more likely to be under stress, and the end result is not likely to be of the highest quality. A good indoor swim team will have a fully harnessed strategy to continually provide the team with some breathing space from the high pressure of setting the team up for improved morale and the elimination of quality deteriorations by stopping the urgent tasks.
Float allows for projects to be protected from a number of traps. Float helps protect projects from more of the "cascading issues" that occur from poorly placed deadlines. Float will aid poorly placed deadlines, OT, critical chains and team burnout. Float helps defend projects from critical chains and team burnout.
To an extent, float provides a defence against project risks. Negation of substantive float provides the defence against risks. By providing float in the Mat of the highest uncertainty risks, the client will be providing a defence against the risks.
For example, while waiting for a vendor you dont know the exact time for, ensure that the activity and all its successors have float so that external factors do not negatively impact your critical path.
Float values should be recalculated after a schedule update so that they can be tracked. When you update the schedule, if it is a significant update, recalculate the float weekly or as needed. What used to look like a 5-day cushion could be gone if the tasks took longer to complete than originally planned.
Plan float wisely. Not everyone has to know Slack. "We have 3 days of float" is not a reason to increase your scope. Communicate with your team on this so that it is used in the correct way.
Floats should not be looked at as a way of relaxing. Just because activity can be delayed without a penalty doesn't mean it should be. Float can be used on multiple tasks, so if you use it on one, it will negatively affect the rest.
Schedule your Slack within your project management. Write down all the assumptions you made regarding the dependencies and constraints regarding float, as well as how you will track everything and your float. This will let everyone know how to use the schedule and the limits that are in it.
When determining the best course of action regarding the use of float or the addition of resources, apply decision tree analysis and the principles of project management. In some cases, it is best to use float; in others, the quicker investment is more advantageous.
What is the greatest mistake? Most people fail to consider that a float in one path can impact all other paths in the project. In multi-branch and multi-converging activity networks, multiple branches can 'share' the float, and using the float in one branch decreases the amount of float available in other branches.
Floating is a concept most people understand, but most people also easily overlook activities or constraints that are just beneath the critical floating activities, nor do they understand the urgency in monitoring non-critical activities with limited float. When nearly all non-critical activities are critical, the outside margins are gone.
Not updating float and slack calculations is a dangerous practice, especially throughout the life of the project. If the calculations have any hope of providing useful information, the calculations must be updated to reflect the current actual constraints and reality of the project. The project is not in its first week, and all floating values associated with the earlier estimates of individual activity dependencies are no longer relevant; the remaining float will not provide the same artificially created confidence.
Do not explain free and total float concepts differently in the same sentence or statement. If one person is told, "You have 3 days of float," that person will understand that as you have 3 days of total float, and that creates a communication gap as well as congestion in the downstream process.
Study aids for the Project Management Professional exams, including example CPM exercises, are available. Nothing is more important than practising problems. It builds confidence and cements the floating formulas in your mind.
The Gantt charts for the actual project work show float using visual indicators. For Gantt charts, most tools show slack as gaps in the timeline or float levels using colour coding.
The critical path templates and network diagram tools also help in streamlining dependencies and the float calculations. Smaller projects can use Excel templates, but larger ones will be better off with dedicated PM software,e as they will manage complexity better and will reduce or modify float values in real time as the Ps software tracks progress.
A PMP cheat sheet with float formulas and relationships is a very useful quick reference as you prepare for your exam and get into project management in your early career.
Being able to calculate slack in project management goes beyond being able to add time to a Gantt chart. It involves shifting your mindset from being a reactive scheduler to being a strategic planner. This principle is true in every PMP exam and every real-life project as well. Implementing float and slack properly is the goal of every successful project, moving it away from chaos. Improved predictability in your schedule and on your team will come when you start managing Slack in any of your projects.
Shashank Shastri is a PMP trainer with over 14 years of experience and co-founder of Oven Story. He is an inspiring product leader who is a master in product strategies and digital innovation. Shashank has guided many aspirants preparing for the PMP examination thereby assisting them to achieve their PMP certification. For leisure, he writes short stories and is currently working on a feature-film script, Migraine.
QUICK FACTS
Yes, a negative float means that your project is delayed or that the deadline is unrealistic. It means that, due to the dependencies and durations, the tasks cannot finish and must be delayed.